Wow. I thought the orchestration of the pier pouring was impressive but I had no idea of the manpower and coordination involved in the pouring of a foundation. Larry Langan and his crew at Foundation Builders were in full force on pour day. We were lucky to have great Saturday weather with clear skies and cool breezes for the pour and they knocked everything out over a single hectic day.
Multiple crews were responsible for simultaneous activities during the pour process. Concrete by its very nature is very unforgiving and time sensitive material. From the moment it’s mixed in the truck its already started to cure and therefore, it needs placement and finishing as soon as possible. In total it took some 30 mixing trucks, each with 10 cubic yards of 3000 PSI concrete, arriving on-site at a rate of 1 every 6 minutes to complete the pour. Two mixing trucks would pull up to the pumper truck side-by-side. One mixing truck would pour concrete into the hopper of the pumper truck while the other mixing truck’s mixture would be prepped. Occasionally, slump would be removed for immediate slump testing and long-term strength testing. Outside the site, Larry would be examining each mixing trucks contents for consistency and adjusting moisture accordingly. Inside, the pour supervisor, Andy, would be prepping each truck and ensuring a constant flow of concrete into the hopper of the pumper truck. From there, the concrete would make its way through the elaborate booms of the pumper truck and into the foundation form. The entire management of the boom and flow of concrete was controlled remotely at the outlet nozzle by a supervisor from Allied Concrete Pumping with guidance from the Foundation Builders crew controlling the nozzle. A primary team, led by Al of Foundation Builders, would ensure that the target portion of the foundation forms was prepped to receive concrete. This included straightening the displaced rebar, poly vapor barrier, and clearing and dirt movements. The nozzle crew would then call for concrete in the working area of the pour and fill in accordingly. Another crew using hand rakes would evenly distribute the mixture while a team member would use a mechanical vibrator in the beams to ensure that there were no air pockets in the pour. This was followed up by a crew using a long aluminum level to flatten out the surface of the pour shortly followed by a team member using a bull trowel to smooth the surface. A finishing team would then use hand trowels to smooth the fine lines and place the J-bolts and various anchors at the perimeter of the slab for anchoring the framing plates.
All the while, various people would be following up this work by removing some of the inner support forms and hand troweling and finishing various portions of the slab as the nozzle work crew moved onward to complete another section. All in all, about 20 people were on the slab simultaneously and it was a sight to behold as they worked diligently and quickly to make sure everything flowed smoothly and consistently throughout the slab pour. The entire pour took about 4 hours to complete and then the finishing work began.
The finishing work consisted of the removal of all interior form supports as the concrete set up. This was followed by more hand troweling and smoothing. Eventually, this was followed up by using a spinning machine trowel and finally, the entire slab was coated with a concrete sealer.
The finishing work itself took 5 hours to complete and no detail was overlooked.
Measurements were verified, slopes and grades were verified, and various portions troweled and re-trowelled to make sure the final product was smooth, consistent, strong, and exactly according to plans and specifications. One of the last, but very critical operations in the finishing process, included the entire family pressing our hand prints into the slab and writing our names above them. Apparently this is not an unusual request and the very busy team at Foundation Builders were extremely accommodating as they guided us through the process (much to the delight of our kids).
The next work day, the crew came back and removed the final form boards leaving a perfect foundation in place for the framing contractor.
Great work guys! Very impressed.